NEW QUESTION # 31
While performing an inspection of a machinery type it is noticed that the attached structure has more vibration that the actual equipment type. This is an example of what?

  • A. Spectral radiance
  • B. Resonance
  • C. Transmitted harmony
  • D. Transmitted Hz

Answer: B


NEW QUESTION # 32
Which of the following statements will be true when a company applies the "lower of cost or market" rule and reports inventory at replacement cost?

  • A. None of the above
  • B. Replacement cost is greater than net realizable value.
  • C. Original cost is less than replacement cost.
  • D. Net realizable value is greater than replacement cost.

Answer: D

Explanation:
When a company applies the "lower of cost or market" rule and reports inventory at replacement cost, net realizable value is greater than replacement cost. The replacement cost is used as the market value when it falls in between the maximum (net realizable value) and the minimum (net realizable value less normal profit).


NEW QUESTION # 33
What is a high level metric used to evaluate the overall effectiveness of a Safety Program?

  • A. Lost time injury frequency
  • B. Near miss report submissions
  • C. First aid case frequency
  • D. Number of job hazard analyses completed

Answer: A


NEW QUESTION # 34
What should be done first to address a gap between your manufacturing performance and World Class performance?

  • A. Review gap analysis to ensure it reflects your current performance accurately
  • B. Assign additional resources to work on attaining World Class performance
  • C. Define the value of the gap to determine its worth to the company
  • D. Develop gap closure plans and begin to implement them

Answer: A


NEW QUESTION # 35
One way to stimulate and motivate your team member is to understand what drives human beings. Which desire does not motivate most of the time?

  • A. Desire for Paycheck
  • B. Desire for Recognition
  • C. Desire for Competence
  • D. Desire for Ownership

Answer: A


NEW QUESTION # 36
Time when the asset is scheduled to run divided by total available time expressed as a percentage. → UTILIZATION TIME

  • A. True
  • B. False

Answer: A


NEW QUESTION # 37
Arrange the following cascading indicators in descending order:
1.Schedule compliance
2.Return on Invested Capital
3.Uptime
4.Equipment reliability
5.Plant (Facility) Profitability
6.Production volumes

  • A. 2, 5, 6, 3, 4, 1
  • B. 2, 5, 6, 4, 3, 1
  • C. 3, 5, 6, 4, 1, 2
  • D. 2, 1, 3, 4, 6, 5

Answer: B


NEW QUESTION # 38
As the maintenance manager at a new plant (facility) you are developing the maintenance workforce strategy for start-up. Select the best workforce attributes for maximum effectiveness, assuming that unit labor costs are equal

  • A. An annual bid and selection of a maintenance labor contractor is performed, using unit-costing of tasks normally required.
  • B. A managing contractor is brought on site to handle all aspects and provision of maintenance labor.
  • C. Operations performing minor maintenance and company multi-skilled technicians performing complex maintenance tasks.
  • D. Multi skilled mechanical crafts (trades) and instrument electrical crafts (trades) are hired and developed.

Answer: C


NEW QUESTION # 39
All personnel, salaried and hourly, direct and indirect, who are responsible for executing work assignments pertaining to the maintenance of physical assets and components → Corrective Maintenance Cost

  • A. True
  • B. False

Answer: B


NEW QUESTION # 40
= Training Hours ÷ Number of Maintenance Employees

  • A. Mean Time To Repair or Replace (MTTR)
  • B. Maintenance Training Hours Formula
  • C. Down time Formula
  • D. Uptime Formula

Answer: B


NEW QUESTION # 41
% = [Condition Based Maintenance Cost ($) ÷ Total Maintenance Cost ($)] × 100

  • A. Mean Time Between Maintenance (MTBM) Formula
  • B. Condition Based Maintenance Cost Formula
  • C. Maintenance Training Return on Investment (ROI)
  • D. Equipment Availability Formula

Answer: B


NEW QUESTION # 42
This metric is the cost for the formal training that internal maintenance employees receive annually. It is expressed as cost per employee.

  • A. Limiting Availability
  • B. Maintenance Training Cost
  • C. Condition Based Maintenance Cost
  • D. Maintenance Action

Answer: D


NEW QUESTION # 43
Work done to restore the function of an asset after failure or when failure is imminent. → Corrective Work

  • A. True
  • B. False

Answer: A


NEW QUESTION # 44
the ratio of the benefit to the cost of training maintenance employees

  • A. Maintenance Unit Cost Formula
  • B. Maintenance Training Hours Formula
  • C. Maintenance Action
  • D. Maintenance training ROI

Answer: D


NEW QUESTION # 45
True

  • A. Lagging KPIs are the results of a process. (T/F)
  • B. The failure rate of a component/asset can be calculated by knowing:
  • C. Most of the maintenance costs become fixed at what phase?
  • D. Maintenance Training Cost (per employee) Formula

Answer: A


NEW QUESTION # 46
Measure of the variables inherent in the design that affect availability. In the calculation of downtime, it usually includes only active repair time. It does not include preventive maintenance time and administrative or logistic delays, but does include corrective maintenance downtime

  • A. Replacement Asset Value (RAV)
  • B. Limiting Availability
  • C. CRITICAL ANALYSIS
  • D. Inherent Availability

Answer: D


NEW QUESTION # 47
The amount of time an asset is actively producing a product or providing a service. It is the actual running time. → Uptime

  • A. True
  • B. False

Answer: A


NEW QUESTION # 48
As the maintenance manager at a new plant (facility) you are developing the maintenance workforce strategy for start-up. Select the best workforce attributes for maximum effectiveness, assuming that unit labor costs are equal?
Options

  • A. A managing contractor is brought on site to handle all aspects and provision of maintenance labor.
  • B. Operations performing minor maintenance and company multi-skilled technicians performing complex maintenance tasks.
  • C. An annual bid and selection of a maintenance labor contractor is performed, using unitcosting of tasks normally required.
  • D. Multi skilled mechanical crafts (trades) and instrument electrical crafts (trades) are hired and developed.

Answer: B


NEW QUESTION # 49
A large manufacturing company installed some asset monitoring device large motors that were deemed critical equipment. The monitoring devices engineering with vibration data, acoustic data, as well as operational performance data. What asset management strategy has the company selected for the

  • A. CBM (Condition Based Maintenance/CM (Corrective Maintenance)
  • B. OBM (Operational Based Maintenance/CM (Corrective Maintenance)
  • C. PM (Preventive Maintenance/OBM Operator Based Maintenance)
  • D. CBM (Conditioned Based Maintenance)/PDM (Predictive Maintenance)

Answer: D


NEW QUESTION # 50
Motor current analysis reveals an unbalanced motor current in excess of 40% when the motor is loaded to over
70% of its nameplate full bad ampere rating. What should you suspect and or what should you do?

  • A. Atthe first opportunity, shut down the motor and have motor circuit analysis performed to locate the cause so it can be corrected.
  • B. Order more on-line tests to confirm the problem, allowing production to continue as long as possible.
  • C. Order the motor to be removed from service immediately, since failure due to overheated winding insulation is imminent.
  • D. Do nothing. Current unbalance is normal in a motor that is not fully loaded.

Answer: B